SRSD - Isolation Valve Replacement Project

The Work consists of removing and replacing five plug valves on force mains that have become inoperable on three different sites in the City of San Rafael. On one site belonging to the San Rafael Sanitation District, a new vault will be constructed around the existing force main to house the new valve. On the other two sites, both along Point San Pedro Road, the valves will be replaced by direct bury. This work will be coordinated with the District’s operations and with the Central Marin Sanitation Agency’s Wastewater Treatment Facility to take advantage of a planned system shutdown.

Status

Bidding Closed

Prebid Date7/19/23 1:00pm

Bid Date7/28/23 10:00am

Company & Contacts

San Rafael Sanitation District
Chris Ewers: Chris@EwersEngineering.com  
(916) 521-9696

Location

San Rafael Sanitation District

A mandatory pre-bid site visit will be held on July 19, 2023, at 1:00 PM.
The site visit will begin at 905 Pt. San Pedro Road (Site 3), San Rafael, CA.